Sudin SDA Jakbar Keruk Kali KBB Sepanjang Empat Kilometer

Mud in West Flood Canal Dredged to Minimize Flooding

The West Jakarta Water Resources (SDA) Sub-agency continues to carry out flood prevention programs. One of them is by dredging mud in river bodies, reservoirs, and water channels. It is done to increase water holding capacity during the rainy season.

The work progress has touched 70 percent

Most recently, mud dredging was carried out in the West Flood Canal (KBB) which passes through the West Jakarta area, precisely from Kota Bambu Selatan Urban Village in Palmerah Sub-district to the Kalijodo RPTRA area in Angke Urban Village, Tambora Sub-district.

"KBB mud dredging is a program of the Jakarta SDA Agency, the work of which is carried out by sub-agencies in each region. Work has been conducted simultaneously since September 2023," expressed West Jakarta SDA Sub-agency Head, Purwanti, Tuesday (11/14).

Anticipating Floods, Heru Inspects Mud Dredging in Ciliwung River

She explained the work from South Bambu City to Angke Urban Village was carried out for four kilometers with a dredging depth of 1.5 meters.

The work is divided into three segments, namely segment one in the South Bambu City area deploying two excavators, and segment two in the Season City area deploying four excavators, two each on the river body, and two on land. Lastly, or segment three in the Kalijodo area, four excavators were deployed, two on the river body and two on land.

As for the work in Angke Urban Village was completed. Currently, the work is still ongoing in the Bambu Selatan City and Season City areas.

"The work progress has touched 70 percent. Hopefully, it can accommodate rain water in large quantities in order to minimize flooding from the KBB," he stated.

Linked News
Popular News indeks
  1. Jakarta Announces Rp 1 Fare for Transjakarta, MRT, and LRT on August 17

    access_time13-08-2026 remove_red_eye901 personAldi Geri Lumban Tobing
  2. Abdul Muis Building Fire Response Nears Completion, No Fatalities Reported

    access_time08-08-2026 remove_red_eye604 personAldi Geri Lumban Tobing
  3. Pramono Urges MUI to Strengthen Synergy in Maintaining Jakarta’s Harmony

    access_time12-08-2026 remove_red_eye579 personDessy Suciati
  4. Jakarta Ensures Public Services Stay Operational After Abdul Muis Building Fire

    access_time08-08-2026 remove_red_eye572 personFakhrizal Fakhri
  5. Fire Site in Utan Kayu Utara Being Cleared

    access_time11-08-2026 remove_red_eye432 personNurito